One of the worst cases of illegal dumping in recent years is that which occurred on the S. Yaffa & Sons, Inc. (the Yaffa) Site. For a period exceeding three years, nearly two entire blocks of private property in the Bergen Square section of the City of Camden have been subjected to illegal dumping and the storage of imported contaminated fill material by the operator/owner of the site. The mounds of more than 40,000 cubic yards of solid waste—including contaminated soil, construction and demolition debris—rise to up to 45 feet or over two stories in height. These piles engulf the 600 Block of Chestnut Street and loom over its surrounding residential neighbors. Sampling of the soil pile material indicates the soil is contaminated with metals, pesticides, volatile and semi-volatile organic compounds at levels similar to historic fill material that is found throughout the City of Camden. Prior to importation of the fill material, this site was allegedly used as a junkyard.
On behalf of the City, Camden Redevelopment Agency (CRA) is tasked with conducting the environmental assessment and cleanup.
Accomplishments to date:
-
County Health Violation: Under the authority provided by local health ordinances, Camden County issued a notice of violation on August 12, 2022. The owners of the Yaffa property were given 30 days to remove the contaminated soil. Upon expiration of the 30-day period, the owners failed to abate the public health issue by removing the contaminated soil piles. This prompted the City of Camden, via CRA, to proceed to enforce the ordinance. On September 26, 2022, the locks to the gates were cut and removed. Removal of all soil pile material is on track to be completed in 2023.
-
Property Ownership: Due to unpaid property taxes, the City of Camden was able to foreclose on the Block 331 portion of the property in November 2022. The City is now the owner of the Block 331 tax lots.
-
Funding for Soil Pile Removal: Over $5 million in funding has been secured to conduct the environmental investigation and remove the soil piles from this site:
-
NJEDA’s Brownfield Impact Fund: $157,142 grant
-
CRA’s Brownfield Revolving Loan Fund: $164,560 grant
-
State Hazardous Discharge Site Remediation Fund: $54,765.32 grant
-
City Allocation of Federal Pandemic Relief Money and State Transitional aid: up to $5 million grant
-
CRA did oversee removal of the soil piles in three phases with the final phase now complete.
-
During the testing of the soil piles, 15 drums were discovered on this property. The drums were removed and properly disposed of in March 2023.
-
All the soil piles were removed from Block 331 as of June 2024. An environmental assessment is now complete, and environmental investigation is nearing completion
YAFFA SITE COMMUNITY MEETING UPDATES: Tuesday, November 12, 2024 at 5:30 PM at KIPP Cooper Norcross High School, 740 Chestnut Street, Camden NJ 08103
Yaffa-Public-Meeting-Flyer-NOV2024_English
Yaffa-Public-Meeting-Flyer-NOV2024_Spanish
Site Map: Click HERE
Site Map for Soil Removal: Click HERE
Soil Piles B and C Removal in October 2023
Location: 618 Chestnut Street (BLOCK 331, LOTS 41, 48-50, 52, 54-65, 67, 75, 80 & 114)
Contractor Work Plan for Soil Piles B and C Removal: Click HERE for work plan
Truck Route: Click HERE
Yaffa Soil Pile Removal Schedule: October 2023 to February 2024 (anticipated)
Soil Pile D Removal Completed March 2023
Location: 1112-1114 S. 6th Street
Contractor Work Plan for Soil Pile D Removal: Click HERE for work plan
Soil Pile A Removal Completed May 2023
Location: 619 - 635 Chestnut Street
Contractor Work Plan for Soil Pile A Removal: Click HERE for work plan
Live Camera Feed: https://share.earthcam.net/tJ90CoLmq7TzrY396Yd88GXoHacZNtJxa1wCII6E7v4!/soil_removal_project/camera/view_1
Waste Pile Sample Results: